03/10/2015
– 04/02/2015 WestPro, LLC, Wyoming Refinery,
Newcastle,
Wyoming
SD/TA Piping Planner/Scheduler
·
Using
client provided Piping Isometric drawings, I calculated all man-hour’s
required to fabricate, test and install the piing spools for the April 2015
Heater Piping Upgrade SD/TA Tie Ins. I also created a BOM per piping
Isometric drawing, along with a stepped out plan of activities needed to
install each line.
·
I then
assisted a Sr. P6 Scheduler in building a Level 1, P6 based rough schedule
for the Tie In work required during the TAR phase of this project using the
information I had accumulated from the drawings and various walk thru’s
with the contractor already engaged with performing the TA work.
·
Again using
client provided Piping Isometric drawings, I calculated all man-hour’s
required to fabricate, test and install the piing spools for the concurring
April-October 2015 Exchanger Modules Piping Upgrade project. I created a
BOM per piping Isometric drawing for this project as well, along with a
Man-hour total and step out package for each Line to be erected.
·
Using my
Level 1 schedule, I added the second TA to it and I helped the scheduler to
perform the necessary logic ties and manipulated the milestone Activities
to complete this schedule in the timeframe that my contract was negotiated
for.
·
I was given
a clean ROF after successfully completing this project.
02/16/2015
– 02/27/2015 WestPro, LLC, NCRA Refinery,
McPherson,
Kansas
SD/TA Planner
·
Planned various
work packages included in the March 2015 Refinery SD/TA in the Area 426A
Vacuum Unit. Planned the activities and man-hours for the Tube replacement,
I&E upgrades, and burner replacement work on the HF-0011 Vacuum Heater
utilizing Turner Industries Quick Plan estimating software package.
·
Assisted
QAQC Department by performing walk thru’s on work packages to capture new
work done during PRE-T/A phase that could possibly be signed off as
COMPLETE by Plant Operations.
·
Due to
Turner Group’s corporate policy concerning third party access to their
company data bases, my position ultimately was eliminated after a two
week period when it was deemed by upper corporate management that company
policy specified that I could not have the access, that I needed to
perform the full scope of my SD/TA duties.
·
I received
a clean, reduction in force lay off and all demobilization monies I had in
my contract, with an apology from the site management who had hired me, for
my troubles.
11/01/2013
– 12/19/2014 WTMC, BP-AMOCO Refinery,
Whiting,
Indiana
Jr. Scheduler
.
·
I was
tasked with assembling relevant equipment data used in creating standard
work packages to relieve the backlog of Relief Valve Compliance PPM’s found
within the Hydro Power South, North and Utilities areas at the BP Whiting
refinery. I performed this work utilizing SAP inside a computer based maintenance
system. I completed this task successfully and my contract was extended
thru the end of the 2014 calendar year.
·
Personally
walked out and estimated/planned routine maintenance work and built work
packages containing BOMs, P&IDs, pictures of the work being
anticipated, MSDS’s, and previous Inspection reports. Worked with the union
workforce supervisors to help define 2 month look ahead work schedules to
perform the work included in my packages. In the process of doing this, I
made notes on deficiencies I had found pertaining to relief valve status,
its physical location, and whether or not they were still in place or had
been removed from service for a wide variety of reasons after the plant had
went thru a major renovation during the 2009-2013 time period.
·
I sent this
information up to BP operations/ management, who then directed me as to
whether I should deactivate or flag these valves for deletion in the active
SAP work schedule. During this process I reviewed and corrected any/all
resource code errors contained in the Work Plans and or active Maintenance
Orders at the request of the Scheduling Department.
·
Developed
and implemented routine naming conventions for all the work orders found
within SAP pertaining to my areas of responsibilities in the various
Hydropower operations units.
·
Upon
completing the Relief Valve Project, I was similarly tasked to work on the
backlog of Pump Repair PPM’s in both the APS and FCU Complexes at this same
refinery, again tasked with implementing revised routine naming conventions
for all the work orders found within SAP pertaining to my new areas of
responsibility in both the APS and FCU operations units.
·
I
successfully completed this last task and was informed that my last work
day onsite would be 12/19.2014.
09/16/2012
- 05/16/2013 Zachry Holdings Incorporated, San
Antonio, Texas Piping Estimator 11
·
Piping
Estimator 11- Assigned to review
pre-bid estimate documents so as to determine all piping quantities
required to perform conceptual work-hour and materials labor and cost
estimates on a variety of multi million dollar power generating plants
scheduled to be constructed throughout the US. This included coal, natural
gas, and nuclear power facilities, as well as a few petro chemical process
piping projects. I also worked on a number of smaller scale
replacement in kind piping projects while with this company.
·
Utilized
ZHI’s in house, historical project database to help establish baselines to
base various conceptual estimates upon when documentation was not available
or forthcoming from our clients and working partners.
·
Estimated
all craft man-hours, material costs, labor rates, scaffolding requirements,
BOM’s, insulation needs, hydro-testing, stress relief and x-ray needs, as
well as painting requirements and construction equipment needs.
·
Utilized
both of ZHI’s PF$ and Hard Dollar Pipe estimating software systems while in
this position.
·
Work on a
number of smaller scale replacement in kind piping projects.
·
Performed
jobsite visits to verify the accuracy of the bids we had produced.
·
My position
was deleted due to general work downturn in the economy.
02/06/2012-
05/02/2012 Clifton Planning Inc. Wynnewood Refining,
Wynnewood, OK Capital Projects Planner
Contract
Capital Projects Planner- Planned, documented and was
responsible for all activities to be performed on a variety of Capital Work
Projects to be completed prior to and or during the 2012 Wynnewood, OK
Refinery plant-wide SD/TA.
·
Gathered
all relevant historical documentation from clients computerized maintenance
database and records, utilizing Clifton Planning’s proprietary, template
based software to plan and then perform Inspection’s driven Capital
Projects work. Estimated all man-hours, scaffolding requirements, BOM’s,
insulation needs, Hydro-testing materials, and equipment needs.
·
Responsible
for Estimating and Planning (35) separate piping projects relating to
multiple unit Heaters, Drums, Towers, Exchangers, Fin Fans, Filters and
Pumps.
·
Determined
all post FW- Hydro Test Blinding needs, ordered the necessary bolting and
gaskets required, and assembled and marked up a set of relevant P&ID
drawings for each Capital Work Package by Work Order.
·
Performed
construction contractor oversight duties to verify and document actual
progress made in the pre-turnaround, capital project installation phase of
this project.
·
Wynnewood
Refinery sold, and new corporate management out of Kansas takes over the
Capital Project phase of this turnaround. My contract concluded.
11/14/2011-
01/20/2012 BEI Group Valero
Refinery, Houston, TX Contract SD/TA Planner
Contract
Shut Down/Turn Around Planner- Planned,
documented and was responsible for all activities to be performed during
the Fluid Cat Cracking Unit SD/TA at the Valero-Houston Refinery, relating
to unit Drums, Exchangers, Fin Fans and Towers.
·
Gathered
all relevant historical documentation from clients computerized maintenance
database (Innovative Plant Server) necessary to plan and then perform
10-year Inspection driven work. Estimated all man-hours, scaffolding
requirements, insulation needs, material and equipment estimates.
·
Built
various stepped out work templates for use by Contract Schedulers in
developing the project schedule.
·
Built an
Excel spreadsheet to capture all of the possible bolting replacement
requirements for the various Heat Exchangers being disassembled and sent
out for repairs, as well as a traveler package (Tag, MSDS, U-I Form) for
each of the items being sent.
·
Identified
(size, length and thread style) plug and gasket needs, then spoke with
local approved vendors to determine availability for use in Fin Fan
Overhauls and cleaning.
·
Walked 51
AWR PSV’s to be included in and serviced during the TA that has been
postponed until later this Fall 2012.
07/18/2011-
10/16/2011 Fluor- TRS Services DuPont-Yerkes,
Buffalo, NY Contract Maintenance
Planner
Contract Maintenance Planner- Tasked with Performing a Review of this Manufacturing facilities
Work Plans and maintenance planning procedures. Was then tasked with making
changes to various work documents and related procedures accordingly, with
a heavy emphasis on Safety and OSHA regulatory compliance.
§ Edited then reprinted for further
review, previously marked up historical database Work Plans for both
Operations personal and Plant management. Worked on reducing the backlog of
data entry work connected with completing work packages in this facilities
SAP maintenance and tracking system.
§ Walked out various routine jobs
with maintenance planning staff and wrote new Work Packages to cover the
work that was discovered. These were then to be used as generic templates
to help streamline and reduce redundant effort in the overall Planning
process used at this jobsite.
§ Wrote the 80+ Job work plans
(mechanical, instrumentation, and electrical) to be utilized during a three
day, CORIAN Unit, Sheet Line1-SD/TA that was scheduled for 08/22/2011.
Assisted the various DuPont planners in streamlining and organizing the
file structure used to save and store all work plans generated in both the
TEDLAR and CORIAN sheet production lines at the Yerkes facility.
§ Completed a similar review and
wrote in excess of 175 Job work plans (mechanical, instrumentation, and
electrical) for the TEDLAR Unit, Production line SD/TA that was scheduled
for/completed between 9/29/2011 and 10/12/2011. It was deemed that I had
successfully completed this assignment after the 2011 TEDLAR SD/TA was
over.
05/13/2011
– 6/13/2011 Innovative Turnaround Controls, Pasadena,
Texas BP - TCR, Texas City,
Texas SD/TA Piping Field Planner
· SD/TA Piping Field Planner - Walked out, then estimated and
Planned multiple Piping Packages for the UU3 SD/TA scheduled for late 2011.
To include stepping out each package (350+), taking pictures of each work
list item, and then estimating all man-hour, material, scaffolding, insulation
and lifting equipment needs to perform these jobs as determined by BP
Engineering.
· Utiliized ITC’s proprietary,
planning database system “Innovative Plant Server” to capture and document
electronically, all TA work to be performed.
07/20/2010
– 03/25/2011 KAP Project Services LaPorte, Texas
DOW -
Rohm & Haas SD/TA Group - Field Planner/Estimator
§ SD/TA Planner/Scheduler – Utilized clients (DOW)
Computer Maintenance Management System and SAP program to plan and estimate
all work being performed on a $4.6 M project at the Rohm & Haas
Chemical Plant in Deer Park, Texas for the 2011 NBA Unit MIT- Inspections
SD/TA. This also includes locating and documenting all material and
logistical needs for the Control and Pressure Relief Valves to be removed
and sent out for Repairs during SD/TA.
§ Gathered all relevant historical
documentation from clients computerized maintenance database necessary to
perform man-hour, scaffolding, insulation, material and equipment estimates
and then build individual work packages.
§ Coordinated with Material
Procurement to assure on time delivery of all long lead material needs.
Contacted various outside vendors for quotes on misc. specialty item
procurement.
§ Walked out and developed various
piping job plans, including manpower and material estimates for the Capital
Projects work group in the NBA Tank Farm area.
§ In SAP, documented all BOM needs,
proper spec requirements, complete activity and resource needs, and
provided Operations and Inspections with complete job scopes for WO#
release. Filled out database forms and then imported this data into a P3.1
plan load for use by project schedulers.
§ Will serve as project coordinator
during TA to monitor and assist contractor (JVIC) performing scheduled
work.
I created a
Confined Space Entry Manual for all Equipment being entered for Inspection
or Repairs during this TA. It is to be used by DOW Operations as a training
manual after TA completed. I also included a separate PowerPoint slideshow
for each Equipment package that showed every Blinding point and or
Instrument to Disconnect required for each Entry permit, segregated by
Equipment Number from Operations.
02/01/2010
– 03/05/3010 The Mundy Companies Pasadena, Texas
SD/TA Planner/Scheduler
§ SD/TA Planner/Scheduler – Monitored Daily Job Progress and
Performed schedule updates in a MS Project based SD/TA schedule while
planning all discovery work w/ related material needs in an SAP database
system for the 6 week, $1.8 M Evalca Spring 2010 plant wide PSM SD/TA in La
Porte, Texas. Walked out daily scheduled jobsite activities to visually
verify actual daily progress, then updated planning war board for client,
while maintaining all job files, and printing out the daily work tickets
for each crew foreman.
12/2008
to 1/15/09 The Turnaround Management Co. Kemah,
Texas
Maintenance
PSV Planner
§ Maintenance PSV Planner - Assisted Exxon-Mobil, Torrance,
Ca. Refinery Planning Group to expedite and complete their existing
scheduled PSV Inspection and Repair Program for 2008, utilizing their in
house TABWARE planning software package.
03/2006
to 10/2008 Fishbone Solutions
Ltd. Kemah, Texas.
SD/TA Planner/Field
Scheduler/Estimator/Coordinator/Designer
§ Lead Planner/Piping Estimator – Routine Maintenance & $2.5M
Project/New Construction – Flint Hills Refinery, Odessa, Texas
§ Shot and Established All Field
Elevations with Engineering Transit. Field Routed a new 30# & 175#
Steam Condensate Piping System with accompanying process skids, a new
Hydrogen Truck loading rack, and replaced an existing Return/Supply Cooling
Water header thru an operating Olefins unit. Verified All Tie-In Points,
Field Dimensions/Measurements and Produced Detailed Isometric Piping
drawings with BOMs as needed for shop fabrication on these Projects.
§ Estimated all piping and material
quantities along with required man hours for calculating related work
packages to assist development of the relevant budget requirements for the
bid on this field installation.
§ Input Planning Data into
Customized Microsoft Planning Platform, in Preparation for Migration to
Primavera P3.1 for Windows
§ Served as designated Client Agent
during Project Installation SD/TA Phase supervising sub contractor
performance.
§ Developed multiple work packages
for Olefins/Poly Plant, 10 year PSM Inspections SD/TA.
§ Lead Planner/Field Scheduler – SD/TA-TOTAL Refinery, Port
Arthur, Texas
§ Input Planning Data into
Customized Microsoft Planning Platform, in Preparation for Migration to
Primavera P3.1 for Windows
§ Composition of Logic Ties in a
Complex String of Activities in Excess of 11,000 +/- with Budgetary Amounts
of Approximately $60mm for Multi Unit Turnarounds
§ Performed Schedule Updates by way
of Data Input into Primavera P3.1 for Windows
§ Provide front end loaded schedule
as well as complete ready to execute resource loaded logic driven schedule
§ Responsible for Material
Procurement according to Pertinent Engineering Standards and Plant
Specifications
§ SD/TA Piping Planner/Estimator- BCIP SD/TA Project, Exxon-Mobil
Refinery, Beaumont, Texas.
§ Participated in Field Surveys with
Exxon-Beaumont Engineering to verify and or determine all new piping work
to be performed during the Fall 2005 SD/TA.
§ Established and labeled 350+ new
process piping Tie In points to existing process piping systems in the
field.
§ Calculated material quantity
takeoffs and man-hours required for bid proposal and pre-T/A work
assessment.
§ Built work packages, and assembled
all required documentation (equipment and Isometric drawings, Pipe
specifications, MSDS sheets, safety requirements, Inspection and testing
forms, and QA/QC documents) to be given to and used by various
subcontractors performing these piping revisions.
§ Planned Various Piping &
Mechanical Jobs. Assembled Detailed Work Packages on PC in an Access based
database.
§ Assembled PSV Travel documentation
packages and tracked work progress for 500+ safety devices being sent out
for R & R at offsite repair facilities.
§ Tracked Work Progress during
various T/A’s in both Primavera P3.1 and Microsoft Project.
§ Renewed US Passport (2007)
|
01/2006–03/2006
P2S Inc. Lake Charles, LA. Pipe Foreman
§
Piping
Frontline Supervisor - Shutdown/Turnaround Assignment.
§
Refinery Process Piping Upgrade
T/A, CITGO Refinery, FCC Lake Charles, LA.
§
Re-Tubed Piping and Retrofit
Structural Steel on (3) Furnaces in FCC Unit.
§
Made major piping modifications
and performed weld overlays throughout existing Cat Cracker Unit as
determined by CITGO Inspections Department..
|
|